[Update 19/07/2023] Construction Progress of Chung Ah Vina Factory Expansion Project

The expansion project of Chung Ah Vina’s plastic filter film manufacturing facility has now been under construction for four months since groundbreaking, reaching approximately 70% of the planned schedule.

During execution, the Site Management Board encountered certain challenges related to weather conditions, manpower, and material supply. However, with strong determination to stay ahead of schedule, the Board worked closely with all relevant departments to develop and apply the most effective construction measures.

At present, the stormwater and wastewater drainage systems, as well as the facility’s foundation, have been completed by around 90%. The Site Management Board is now carrying out the installation of trusses and columns for the production workshop. Meanwhile, ground treatment for the workshop floor has also reached 80% completion.

For the office building, construction teams are installing the roof for the second floor and finishing plastering the external walls of the first floor.

The project is expected to be completed and officially handed over to the investor on September 6, 2023.

On-site images as of July 19, 2023:

Nhà văn phòng đang được đội xây dựng tô trát tầng 1 & chuẩn bị lắp đặt mái tầng 2

Office building: the construction team is plastering the first floor and preparing to install the roof for the second floor.

Tầng 2 nhà văn phòng đang xây dựng hoàn thiện hệ vách

Second floor of the office building: wall partition works are being completed.

Khu vực nhà xưởng sản xuất đang được lắp đặt cột & kèo

Production workshop area: installation of columns and trusses is in progress.

Công nhân đang lắp đặt, trám lại hệ khung cửa sổ xưởng sản xuất

Workers are installing and sealing the window frames of the production workshop.

Overall view of the Chung Ah Vina project from the outside.