SERVICES FOR PERFORMING CONSTRUCTION LEGAL PROCEDURES

Nam Trung provides professional, comprehensive construction legal procedures services, ensuring to support customers in completing legal documents and records in full and in accordance with legal regulations. With a team of experienced legal experts, Nam Trung is a reliable partner for all of your projects and works.

Commitment from Nam Trung:

  • Support from A to Z in all construction legal procedures.
  • Ensure transparency and clarity in all processes.
  • Always accompany customers throughout the construction process.

Types of legal construction carried out by Nam Trung

– Consulting and implementing procedures for applying for detailed planning permission 1/500.
– Ensuring the correct legal process and requirements of the competent authority.

1/500 planning implementation process:

  • Step 1: Survey the current status and collect relevant information.
  • Step 2: Prepare a detailed planning map at a scale of 1/500.
  • Step 3: Prepare legal documents related to the planning.
  • Step 4: Submit the application and request appraisal opinions from the competent authority.
  • Step 5: Complete and receive the detailed planning permit 1/500.
 

– Prepare construction permit application.
– Support for construction permit application for housing, commercial and industrial works.

Construction permit application process:

  • Step 1: Survey the current status of the land and collect planning information.
  • Step 2: Prepare construction design documents in accordance with regulations.
  • Step 3: Prepare and complete necessary legal documents.
  • Step 4: Submit construction permit application to competent authority.
  • Step 5: Monitor and supplement documents if requested by competent authority.
  • Step 6: Receive construction permit when the application is approved.

– Consulting and implementing fire prevention and fighting permit application.
– Ensuring compliance with fire prevention and fighting safety standards.

Fire prevention and fighting permit application process:

  • Step 1: Survey the construction and evaluate factors related to fire safety.
  • Step 2: Prepare a fire prevention and fighting system design file according to standards.
  • Step 3: Prepare necessary legal documents and technical files.
  • Step 4: Submit the application for a license to the competent Fire Prevention and Fighting Police agency.
  • Step 5: Coordinate with competent authorities to conduct on-site inspection and acceptance.
  • Step 6: Receive the fire prevention and fighting license after the file is approved.
 

– Consulting and reviewing construction design documents.
– Ensuring compliance with current legal regulations.

Construction design appraisal process:

  • Step 1: Receive design documents from the investor.
  • Step 2: Check the legality and completeness of the documents.
  • Step 3: Evaluate and review design content, ensuring compliance with technical standards.
  • Step 4: Conduct field inspections if necessary.
  • Step 5: Prepare appraisal report and propose adjustments (if any).
  • Step 6: Approve and complete appraisal process.
 

– Complete the dossier and submit it to the competent authority.
– Ensure fast progress.

Procedures for completing the construction procedure:

  • Step 1: Check and collect all legal documents related to the project.
  • Step 2: Prepare the completion drawing and complete the completion dossier.
  • Step 3: Submit the completion dossier to the competent authority.
  • Step 4: Coordinate with the competent authority to inspect the actual construction.
  • Step 5: Edit and supplement the dossier if required.
  • Step 6: Receive the completion permit when the dossier is approved.