[07/07/2023] Production Progress Update for CSWind Project – Wind Tower Factory Expansion

The CSWind project – wind tower manufacturing plant expansion is one of Nam Trung’s key projects in 2023. For this reason, we have set two top priorities: product quality and on-time delivery.

At present, our entire factory workforce is operating at maximum capacity to meet the construction and erection schedule in August.

As of today, production volume has reached 35% of the total project workload, including:

  • Completion of 44 columns for Workshop No. 1
  • Completion of 42 columns for Workshop No. 2
  • Ongoing fabrication and finishing of base columns and gable-end columns for both workshops

Some snapshots from the Nam Trung factory floor:

Công đoạn hàn liên kết bản mã

Welding connection plates

Công nhân thực hiện công đoạn sơn

The painting process carried out by workers

Cột thép thành phẩm

Finished steel columns

Thép thành phẩm được tập kết tập trung chờ vận chuyển

Finished steel materials gathered and prepared for delivery

Xe container vận chuyển thép ra công trình

Container trucks transporting steel to the project site

Source: Nam Trung Marketing