Dooil Factory Project Construction Progress Update [May 27, 2024]

After more than 20 days since the commencement of site preparation and infrastructure works, the Nam Trung construction team has now moved on to critical tasks. These efforts are designed not only to keep the project on schedule ahead of the rainy season but also to ensure the highest standards of safety and security on site.

Our workforce has been consistently maintained at 30–40 people to ensure that every stage of construction is executed on time. At Nam Trung, safety is always placed at the forefront: daily safety training sessions are conducted each morning before work begins, reinforcing our commitment to protecting every member of the team.

Some snapshots from the dooil factory project site:

Công nhân học an toàn

Workers attending daily safety training

Thi công đổ móng nhà bảo vệ

Foundation casting for the guardhouse

Thi công đóng cọc

Pile driving operations

Thi công nền móng cho hàng rào

Foundation works for the perimeter fence

Xây dựng tường rào công trình

Construction of the boundary wall