CSWIND Project – Wind Tower Plant Expansion Construction Progress Update [November 17, 2023]

The expansion project of the CSWIND project – wind tower manufacturing facility has now reached approximately 80% completion. Namtrung is making every effort to finalize the remaining works at Workshops No. 2 and No. 3 to ensure handover before 2024.

Over the past six months since commencement, fabrication and erection activities at the site have been closely monitored and strictly managed. From product quality to safe construction practices, Namtrung has consistently adhered to the highest standards of the steel structure industry.

On-site photos taken on 18/11/2023:

Workshop No. 1: 100% completed

Dự án CSWind: nhà xưởng số 1
Dự án CSWind: nhà xưởng số 1 nhìn bên trong
Dự án CSWind: nhà xưởng số  1 nhìn tổng thể

Workshop No. 2: 75% completed

Dự án CSWind: nhà xưởng số 2 nhìn từ bên ngoài
Dự án CSWind: nhà xưởng số 2 đang lu mặt nền

Workshop No. 3: 85% completed

Dự án CSWind: nhà xưởng số 3, nhà sơn
Dự án CSWind: nhà xưởng số 3 nhìn từ cuối xưởng